Plant-wide Building (Structure) Settlement and Displacement Observation of Fujian Datang International Ningde Power Generation Co., Ltd.

5/6/2022 8:58:15 AM

六宝典最新资料大全

The construction of Fujian Datang International Ningde Power Plant is divided into two phases, the first phase of the project is 2×600MW generator sets, and the second phase of the project is 2×660MW generator sets. Phase I was put into operation and started observation in June 2006, and Phase II was put into operation and started observation in September 2009.

Commissioned by Fujian Datang International Ningde Power Generation Co., Ltd, our company was responsible for the observation of settlement and displacement of buildings in this project. It mainly includes 4 groups of settlement reference network consisting of 12 points for 1 time each, and a total of 97 buildings (structures) in the whole plant, and 1 time for each building (structure) to observe settlement. The plane displacement of coal wharf and heavy cargo wharf was observed once.

六宝典最新资料大全

Settlement displacement observation of the plant began in June 2006 and lasted 23 days from July 14, 2021 to August 5, 2021. During the implementation period, no quality and safety accidents occurred, and no complaints were received from the environmental management department and related parties. We successfully completed all engineering materials and submitted to the owner, passing the owner's acceptance.

 

Add:NO.555 Huaian Road(west),Shijiazhuang City,Hebei Prov. P.C.:0502271   Tel:0311-66723100 66723200 Fax:0311-66723277  
Copy right:China Hebei Construction & Geotechnical Investigation Group Ltd. 2008